Does a delay caused by wildfires fall under Abnormal Weather?

GC 13.3 Unavoidable delay cites Abnormal Weather as something beyond the reasonable control of the Contractor.

What happens when a Contractor breaches the contract?

Situation may require legal advice...but check the GCs for sections relevant to the alleged breach.

Is a broadly worded privilege clause appropriate in Additional Instructions to Tenderers?

A “broadly worded privilege clause” is a concept which the MMCD Association has discussed and rejected, because we anticipate that this will deter bidders

What is the correct Manhole Ladder Dimension?

Please review Standard Drawing S1 with respect to conformance to WorkSafeBC.

Can MMCD Association give design or technical opinions about contracts?

No, but we try to point out sections in the MMCD that might be relevant to the question.

Not yet rated

Will there be a hard copy edition of the Design Guideline Manual?

No, We will license electronic copies only. Those wishing a hard copy are welcome to print the sections of interest from their electronic copy.

What is the most recent MMCD Document available?

The most recent edition is the MMCD 2019 Edition.

2019 MMCD
Not yet rated

Can I print the Design Guideline Manual without the "Printed from MMCD..." watermark across the pages?

No, it is not possible to print without the watermark. The watermark is embedded in printed pages to identify the version of the Design Guidelines from which it is extracted; and to remind users that the content is subject to copyright.