Can the Owner act as the Contract Administrator?

The owner can appoint a Contract Administrator from their staff, but since the CA is in an inherent Conflict of Interest,, there may be a shortage of volunteers!

CCA benefits: Why should my company / municipality use a Certified Contract Administrator?

The CCA is an MMCD contract administration expert. Certified Contract Administrators (CCAs) voluntarily undertake a rigorous certification process through MMCD Association, which includes providing proof of education, practical experience, and professional references, a 16-hour training course, and writing a certification examination – all to ensure a fair process for all parties involved in completing your contract.

What happens when a Contractor breaches the contract?

Situation may require legal advice...but check the GCs for sections relevant to the alleged breach.

Does encountering a concealed condition meet the intent of GC 13.1 Delay by Owner, or GC 13.5 Delays for Additional Instructions?

It depends whether there was an Act or omission by the Owner regarding knowledge of the Unknown concealed condition; and whether the CA responded within the time limits to any written request for Additional instructions.

Is there recourse for the Contractor when an Owner Caused Delay affects Substantial Completion?

The User Guide (10.3.2.1, 10.3.2.2) suggests that Owner caused delays (per GC13.1) entitle the Contractor to reimbursement for costs and lost time. In this case, the CA must act impartially and issue a Change Order for the proven impact, even if the CA was the cause of the delay.