The Contract Considerations Video, "Partial vs. Staged Substantial Performance" should provide the answer.
The User Guide (10.3.2.1, 10.3.2.2) suggests that Owner caused delays (per GC13.1) entitle the Contractor to reimbursement for costs and lost time. In this case, the CA must act impartially and issue a Change Order for the proven impact, even if the CA was the cause of the delay.