Does a delay caused by wildfires fall under Abnormal Weather?

QUESTION

Contractor was to mobilize to site today, but now will not be able to construct due to fires in area and are looking for compensation. Does this delay fall under abnormal weather?

COMMENT

GC 13.3 Unavoidable delay cites Abnormal Weather as something beyond the reasonable control of the Contractor.

Last updated on 23rd July 2020